IT Corridor Project (Rajiv Gandhi Salai)

IT Expressway Ltd (ITEL) is a wholly owned subsidiary of Tamil Nadu Road Development Company Ltd (TNRDC). The Project is implemented in two phases. In, Phase-I the existing Rajiv Gandhi Salai 20.1 km stretch between Madhya Kailash Temple Junction and Siruseri are being improved. In addition to this, in Phase I, the 2.1 km long ECR Link Road connecting IT Corridor at Sholinganallur and East Coast Road is also widened to dual two lane carriageway. The estimated cost of the phase I of the project is Rs.403 crores excluding cost of land, rehabilitation and resettlement. The main carriageway work has been completed. The road has opened for the use of public on 29.10.2008 onwards. The toll collection had commenced from 15th December, 2008.

The works relating to CMWSSB and TNEB are in progress. Once the works of CMWSSB and TNEB are completed, TNRDC will take up construction of service road, foot path, non-motorised vehicle lanes, etc, and the entire work has been completed.

The service road and footpath have been completed from Madhya Kailash to SRP tool junction for 3.0 KM in all aspects.

The land acquisition for the Phase II of the Project from Siruseri to Mahabalipuram is in progress and TNRDC is facilitating it.

For further details, visit www.tnrdc.com

IT Park
Tamilnadu was one of the first states in the Indian Union to formulate a comprehensive IT policy.
More >>
SEZ
A policy was introduced on 1.4.2000 for setting up of Special Economic Zones in the country
More >>
 

Home | About Us | Board of Directors | Project Officer | Site Map | Feedback TIDCO 2006